We share news from the construction site of the LEV CITY HOTEL as of October 18, 2021 :

  • Installation of fiber cement boards on the ventilated facade has begun.
  • We continue to putty the walls on the 3rd and 7th floors.
  • Installation of radiators in rooms proceeds.
  • We install ceramic tiles in the bathrooms.
  • Installation of the air conditioning system continues.

We share news from the construction site of the LEV CITY HOTEL as of October 11, 2021 :

  • Finished plastering the walls on the 1st floor.
  • The walls on the 3rd and 7th floors are being plastered.
  • Installation of radiators in rooms has begun.
  • Installation of the ventilated facade proceeds.
  • The floor heating system is installed on the ground floor.
  • Completed cement-sand screed on the 1st floor.
  • Installation of the air conditioning system continues.
  • Completed waterproofing the atrium.

We share news from the construction site of the LEV CITY HOTEL as of October 04, 2021 :

  • We continue to plaster the walls of the 1st floor.
  • The walls on the 3rd and 7th floors are being plastered.
  • Installation of the power supply system is completed.
  • The installation of a ventilated facade continues.
  • Installation of the floor heating system on the ground floor continues.
  • We continue to pour cement-sand screed on the 1st floor.
  • Installation of the air conditioning system continues.

We share news from the construction site of the LEV CITY HOTEL as of September 27, 2021 :

  • We continue to plaster the walls of the 1st floor.
  • The walls of the 3rd and 4th floors are being plastered.
  • The installation of the power supply system is underway.
  • The installation of a ventilated facade continues.
  • We install a floor heating system on the ground floor.
  • We continue to pour cement-sand screed on the 1st floor.
  • Installation of the air conditioning system has begun.