We share news from the construction site of the LEV CITY HOTEL as of August 2, 2021 :

  • Plastering of stairways continues.
  • Installation of gypsum plasterboard partitions on 5-7 floors was completed.
  • Installed plumbing systems.
  • Installed power supply systems.
  • Installation of a ventilated facade continues.
  • Installation of air ducts continues.

We share news from the construction site of the LEV CITY HOTEL as of July 26, 2021 :

  • Work on plastering stairwells continues.
  • The installation of the power supply system on the 6th floor continues.
  • Completed the installation of double-glazed windows panoramic elevator.
  • We continue to install faucets in the bathrooms on the 7th floor.
  • Work on the installation of a ventilated facade continues.
  • We install air ducts on the 4th and 5th floors.

We share news from the construction site of the LEV CITY HOTEL as of July 19, 2021 :

  • The walls of the rooms and corridors have been plastered. Preparatory work for the plastering of stairs is underway.
  • The installation of the power supply system on the 6th floor continues.
  • Completed the installation of aluminum structures of the panoramic elevator, work continues on the installation of double-glazed windows.
  • We continue to install faucets in the bathrooms on the 7th floor.
  • Work has begun on the installation of a ventilated facade.
  • We install air ducts on the 4th floor.

We share news from the construction site of the LEV CITY HOTEL as of July 12, 2021 :

  • Plastering of walls of the 7th floor proceeds.
  • Work continues on the arrangement of the power supply system on the 6th floor.
  • Work continues on the installation of aluminum structures of the panoramic elevator.
  • We continue to install faucets in the bathrooms on the 7th floor.
  • Preparatory work for the installation of a ventilated facade is underway.
  • We install air ducts on the 3rd floor.